#163: Asset Upgrade & Replacement / 2. Quotes & Vendor Selection / Build Storage Shed, South Lot / Completed
Status: Completed
Due: May 14, 2026
Assignees: Darrell Finley
| Hartley Builders | Prairie Post Frame | Lakeside Construction | |
|---|---|---|---|
| Price, full scope | $21,300 | $23,900 | $24,000 (slab separate) |
| Start | Mid-June | Late July | Early July |
| Permit | Included | Included | Owner to pull |
Selected: Hartley. Lowest price, earliest start, handles the permit.
Created by Vicky Sep 17, 2026