#171: Asset Upgrade & Replacement / 4. Construction & Inspection / Build Storage Shed, South Lot / Completed
Status: Completed
Start: Jun 15, 2026 Due: Jul 10, 2026
Assignees: Darrell Finley

Slab poured 6/17, frame up 6/24, roof and siding done 7/2, doors and electrical 7/9.

Created by Vicky Sep 17, 2026