#50: Asset Upgrade & Replacement / Active projects
Status: In Progress
Start: Aug 24, 2026 Due: Oct 2, 2026
Tag: Breakdown
Assignees: Darrell Finley

Active leak over the east storage bay after the 8/20 storm. Membrane split along two seams plus failed flashing at the HVAC curb, about 3,200 sq ft affected. Repair, not replacement: the rest of the roof has 8 years left.

Where it stands: Ridgeline Roofing on site since 9/14, two of three sections patched. Water test and inspection scheduled 9/29.

Approved Budget: $25000
Vendor:

Ridgeline Roofing


Location:

Building A, east roof section


Asset Type: Roof / Facility
Estimated Cost: $24800
PO Number:

PO-26-0139


Created by Vicky Sep 17, 2026, Edited Sep 17, 2026