#74: Asset Upgrade & Replacement / Active projects
Status: In Progress
Start: Jun 1, 2026 Due: Dec 18, 2026
Tag: Capacity Safety & Compliance

Four dock positions at Warehouse B rebuilt as one project: replace the 1990s mechanical levelers and doors, add LED dock and yard lighting, replace the dock office HVAC, repaint traffic and pedestrian markings. Three vendors, three POs, four departments (Facilities, Maintenance, Warehouse Ops, Safety). Phased so two docks stay open at all times.

Where it stands: docks 1 and 2 being installed, lighting rough-in under way. Docks 3 and 4 follow in October, then inspection, markings and the safety walkthrough.

This is the same template, bigger project example. Each workstream carries its own Vendor, Estimated Cost and PO Number and moves through the same statuses as a standalone project. Dependencies link the steps that cannot overlap. Open Timeline view to see the sequence.

Approved Budget: $175000
Vendor:

3 vendors, see workstreams


Location:

Warehouse B, docks 1 to 4


Asset Type: Roof / Facility
Estimated Cost: $158400
PO Number:

3 POs, see workstreams


Created by Vicky Sep 17, 2026, Edited Sep 17, 2026