Status: Business Case
Due: Dec 17, 2027
Assignees: Felipe
1.2 MW rooftop solar on Plant 1. Expected to cover ~35% of the plant's electricity use.
Requested: $1,200,000, grant-funded. Approved Budget stays empty until the board votes. Decision needed: Board vote scheduled for the November meeting. Grant window closes Dec 31.
Project Code:
Committed: $0
Spent to Date: $8500
Funding Source: Grant
Asset Type: Infrastructure
CAP-27-001
Committed: $0
Spent to Date: $8500
Funding Source: Grant
Asset Type: Infrastructure
Created by Vicky Sep 11, 2026, Edited Sep 11, 2026