Status: Acknowledged
Start: Oct 18, 2027 Due: Oct 22, 2027
Assignees: Elian Glace
Status report for the week of Oct 18 to Oct 22, 2027. The red week. Sent Friday 2 pm, acknowledged by the sponsor the same afternoon, decision made Monday.
RAG Status: 🔴 Off track
Next Milestone: Nov 5, 2027
Complete (pct): 60
Audience: Sponsor
Budget Used (pct): 66
Period:
Next Milestone: Nov 5, 2027
Complete (pct): 60
Audience: Sponsor
Budget Used (pct): 66
Period:
Oct 18 to Oct 22, 2027
Created by Vicky Oct 21, 2026, Edited Oct 21, 2026
Sponsor, Monday Oct 25: approved the $6k contractor standby. Not called in the end, the vendor patch landed Tuesday. Logging the decision here so the next red week has a precedent to point at.
Vicky, Oct 21, 2026