#6: Project Status Report / Week 44 ยท Website relaunch / This week
Status: Acknowledged

Planned this week: migrate 150 pages, finish the pricing page design, start QA on the blog section. Done: 180 pages migrated (ahead), pricing page design approved Thursday, blog QA started a day late. Not done: the search integration spike slipped to next week; nobody was free after the migration push.

Created by Vicky Oct 21, 2026