#11: Agile / Epic: Mobile Experience / 📋 Product Backlog
Status: Ready
Tag: Sprint 2 Spike

Type

Spike — timeboxed to 3 days. The deliverable is a decision, not shippable code.

Question to answer

Does the navigation model in the spec hold up when real people use it, before we commit a full sprint to building it?

Acceptance criteria

  • Clickable prototype covering the primary flows
  • Tested with at least 5 people
  • Findings written up with a clear recommendation: proceed, revise, or rethink
  • Spec updated with whatever the prototype proved wrong

Depends on

On spikes

A spike is sized by its timebox, not by its complexity. When the box runs out, you stop and report what you learned, including "we still do not know." A spike that quietly turns into implementation is no longer a spike.

Business Value: Should have
Story Points: 5
Epic: Mobile Experience
Component: iOS, Android