#44: Agile / 🔄 Ceremonies
Status: Backlog
Due: Aug 9, 2027

Timebox: 2 hours for a 2-week sprint. Who: whole team. Owner: Scrum Master facilitates, Product Owner brings the priorities.

Input

  • A refined, ordered backlog
  • Known team capacity for the sprint (subtract holidays, on-call, support rotation)
  • Last sprint's velocity

Agenda

  1. Why — Product Owner proposes a sprint goal in one sentence
  2. What — team pulls stories from the top of the backlog until capacity is full
  3. How — team breaks the top stories into subtasks and confirms nobody is guessing

Output

  • A written sprint goal everyone can repeat from memory
  • A committed sprint backlog, tagged Sprint N
  • Every committed story has story points, an owner, and acceptance criteria

Rules that actually matter

  • The team decides how much it takes. Nobody assigns capacity to a team from outside.
  • Do not pull a story that fails the Definition of Ready. Send it back to refinement instead.
  • Plan to about 80% of capacity. The other 20% absorbs bugs, interruptions, and the thing nobody predicted. Teams that plan to 100% miss every sprint and then blame estimation.

Common failure

Planning turns into refinement. If you are discovering requirements during planning, your refinement session is broken and planning will always overrun.

Created by Vicky Aug 7, 2026, Edited Aug 10, 2026