#46: Agile / 🔄 Ceremonies
Status: Backlog
Due: Aug 11, 2027
Timebox: 1 hour per week. Who: Product Owner plus whoever can size the work. Owner: Product Owner.
Also called grooming. This is the ceremony teams skip, and skipping it is why their sprint planning runs long and their sprints miss.
Agenda
- Pull items from 📥 Intake — decide: promote, park, or decline
- Write or sharpen user stories for anything promoted
- Add acceptance criteria in Given / When / Then form
- Estimate story points as a team
- Split anything larger than 8 points
- Re-order the backlog so the top is genuinely the next most valuable work
Output
- Enough Ready stories at the top of the backlog to fill the next 1–2 sprints
- Nothing tagged
Needs Refinementin the top 10
Rules that actually matter
- Refine roughly two sprints ahead. No further. Detailed specs for work six sprints out is waterfall wearing a Scrum costume. Requirements will change; the effort is wasted.
- Declining is a real outcome. Mark it Won't Do with a reason. A backlog nobody prunes becomes a graveyard nobody reads.
- If the team cannot estimate it, it is not refined. Send it to a
Spikeinstead of guessing.
Created by Vicky Aug 7, 2026, Edited Aug 10, 2026