Hi, I cant seem to find the filter option to exclude completed tasks after X days in a specific project of mine. How do I enable this filter?

Screenshot 2018-12-19 at 11.56.33 AM.png

Screenshot 2018-12-19 at 11.56.41 AM.png

Created by Jason Dec 19, 2018

Hi Jason, sorry our bad. The 'exclude completed tasks' option will only show when you have task(s) completed 60 days ago. Then, you will see the option to exclude tasks over 30 days.

Michelle, Dec 20, 2018

Hi Michelle, the earliest completed task I could find is completed on 25th October.

Jason, Dec 19, 2018

Hi Jason, it could be that the projects do not have tasks that are completed over 30 days.