#3310: Quire Feedback
Status: To-do

I added tasks through CTRL + C and CTRL + V in the tool with dates of June 5th, but these tasks are not appearing as overdue automatically and the date has already passed. . In the graphical report this activity still appears as being scheduled for today .I imported some activities today, however dated June 7, however, the tool does not put the activity as overdue and appears as if it were planned to do today. This problem only occurs when it is via spreadsheet import. This occurs when a start and end data option is used, for example: if a task is started with data from June 5th, it will not occur as a delay.

Created by Rosana Mendes Jun 9, 2020, Edited Jun 9, 2020

@rosana.mendes - in Quire, if a task only has a start date in the past with no due date, this task belongs to Today.

if the task has both start and due dates, and both are in the past, then this task belongs to Overdue.

Peggy, Jun 10, 2020