Pessoal, há como criar um estado para que apareça em um quadro sem o seu percentual de conclusão? A ideia é ter uma coluna para simples consulta (exemplo um repositório de documentos importantes daquele projeto). Obrigado!
Hi Danilo - Sorry. I don't speak Portuguese so please let me know if I have mistaken you feedback.
At the moment, you won't be able to add a status that is not associated with a percentage. However, you can create multiple status that has 100% and named it as Cancelled, Won't do, or even Notes, etc. The tasks that are added to this status will act the same as a Completed task; they will not show in Tree view when you filter by Active Tasks. I hope this helps. Please let me know if you have any questions. Thanks.


Peggy, May 12, 2021
Hi Danilo - Yes, when you have set the percentage to 100%, it won't show in the List anymore (unless you set to show All Tasks). Or you can try out Monish's method, setting the percentage to 99% or other percentages at the moment. Thanks!
Peggy, May 14, 2021
Hi, Peggy! You understood my question perfectly. Thankyou. I tried your suggestion, but it seems strange, because when you use 100%, the task (document library, for example), appears crossed out, which does not work well. If possible, keep that suggestion in the list. In the trello I did it easily. Best regards!
Danilo Navarro Filho, May 12, 2021
⭐️ We have closed your thread in order to optimize the performance of the Quire Feedback Forum. Please see our Quire Feedback Official Guideline for more information.
If the request/feedback wasn’t answered or the issue hasn’t been resolved in the newest version, please leave a comment below, the Quire team will be notified.
Peggy, Jul 16, 2021
@professornavarro you can set it to 99%, it would seem 100%, yet stay in the list
Monish, May 14, 2021