#4698: Quire Feedback
Status: Completed

I have a repeating Task that I want to show a Start Time and Stop Time for. The only way to do that is to have Start Date and a Stop Date even though they are the same. Let's call this an SDT2Task. I could live with that, except that when I list my Tasks by date and time, the list puts the SDT2Task below the others. I would like to see the list treat the Start Date and the Start Time as if the Stop Date and the Stop Time didn't exist, and if I display the list after the Stop Time, the Task would be shown as overdue. I hope I explained that clearly.

Created by Alvin Orzechowski Jun 22, 2021

May have found my own answer. Selecting the Group option Due Per Day gives me what I'm looking for—I think.

Alvin Orzechowski, Jun 22, 2021

Hi Alvin - I will close this thread for now. You may reach out again if the way you find is working for you.

Peggy, Aug 11, 2021