Hi, as in the title, I would like to see the number of tasks completed over time.
However, the overview page only shows me tasks I've completed over the last 30 days and none after, as if they've been archived or deleted.
I've tried changing the 'Exclude completed task in ___' option to None, but that does not solve the issue in My Tasks overview. Hope to get your help with this, thanks!
William, Dec 5, 2021
Hi William, to see the number of tasks completed in My Tasks, you can filter your completed tasks by filter bar in Tree view. You can follow the screenshot that I provided here. First, select the complete task, and then group by create per week. Next, you can select all the tasks and then see how many you have completed at the bottom. I hope this is helpful 😃



Golda, Dec 1, 2021
Hi Golda! Apologies for the late reply. Yes, that is correct, I would like to see the graph include tasks that were completed more than 30 days ago.
It's my understanding that the graph should look a little more like this?
William, Dec 5, 2021
Hi Golda! Thanks for the reply. Unfortunately I can't seem to view the images you sent, but I think I understood what you meant. 😃
I don't think this is what I wanted to do though, I was looking to view this in the chart in the overview tab? I attached a photo for your reference. As you can see, the graph seems to completely ignore all completed tasks after 30 days, and I'm not sure how to make it not do that. Thank you for your help!
William, Dec 2, 2021
Hi William, I have passed this issue to our team, and our team will check into it further. In the mean time, I will keep you posted if we have any updates. Thank you 😃
Golda, Dec 7, 2021
Hi William, regarding this concern, our Product Team has resolved this issue. Please refresh your Quire page to get the latest version and kindly let us know if the issue still persists. Thank you.
Golda, Dec 13, 2021
Hi Golda, thank you so much for your help and thank you to the product team as well for helping with my small request! Hoping you all have a good day. 😃
William, Dec 17, 2021


Hi William,
According to the screenshot that you provided, there are 29 completed tasks in My Tasks. This number is the total number of all tasks that you have completed since you started using Quire. You mentioned that you want to see the completed tasks after 30 days. I would like to double check about this, do you mean you want to see the tasks that was completed more than 30 days ago? Looking forward for your reply. Thank you.
Golda, Dec 3, 2021