Hello, I am looking for several things. I am handling several consecutive projects with the same general tasks to be performed (task A must be done Dday - 10, task B at Dday-7, task C at Dday -3 and so on). I saw several ways for getting tasks in Quire (copy/past, using csv). This is very useful. As mentioned, some tasks need to be done a certain time prior a certain Dday (for example delivery day). I could not find an effective way to do so. Is there a way to do automatically?

Created by Jean-Baptiste Vanderstichelen Apr 19, 2022

Hi @Jean-Baptiste_Vanderstichelen-55, I'm afraid we do not have the option to set an automatic deadline of certain days prior to the delivery day. You will have to set the deadlines manually.

Nevertheless, I will pass your feedback to our Product Team for further discussion. I will let you know once we have an update. Thank you

Golda, Apr 20, 2022