#5669: Quire Feedback
Status: Completed
One of the columns I have enabled in Timeline grid view is "Estimate". Currently, when I click that column for a task, it brings up the Details side panel for that task, and I'll have to click add estimate to bring up the Add Estimated Time dialog. It'd be great to be able to input a time estimate directly from the Timeline Grid view.
Created by (deleted-PFDH) Feb 10, 2023, Edited Feb 16, 2023
Hi @GTD, Thank you for your suggestions! Currently, you will need to add a time estimate in the detail panel. But I agree that adding a time estimate directly in the grid view will be a great improvement. I will bring your feedback to our Product Team for further discussion. I'll get back to you when we have any updates!
Golda, Feb 10, 2023