#6105: Quire Feedback
Status: To-do

Maybe I'm missing something, if so please let me know. But it appears that adding or removing a task from a sublist does not result in any update in the activity log for the task. As such, you have to ask manually who did it and hope they are still following the task to find out why they might have done so.

It would be great if this appeared in the activity log, like other activities.

Created by Jason Aug 22, 2024, Edited Aug 23, 2024

Hi, When a member adds or removes a task from a sublist, this activity is logged in the project activity log. To view it:

  1. Go to your project and click the Overview tab.
  2. Scroll down to Recent Activities.

Please note that the log currently does not include the task name. It only shows who edited the sublist and the name of the sublist that was edited. We recognize this may not fully address your needs, but rest assured, we have passed your feedback to our team for further review and will inform you of any future updates. Thank you.

Golda, Aug 27, 2024

Hi, At the moment, we don't log activity when a member adds or removes tasks from a sublist. We will share your feedback with our team for more discussion. Once we have any progress related to your feedback, we will let you know. Thank you.

Golda, Aug 23, 2024