#6244: Quire Feedback
Status: Completed
Dear Customer Service,
I was wondering if there might be a way to keep seeing completed tasks in the timeline view? Every time I change a task's status to completed, it disappears from the timeline view. I would really appreciate it if there was a way to keep seeing all completed tasks in the timeline view.
Thank you so much!
Created by fexupery Jan 13, 2025
Thank you so much for providing such a clear and well-explained solution. I truly appreciate the time and effort you put into helping me
fexupery, Jan 14, 2025
Hi, To show both active and completed tasks, you can navigate to the filter icon, click on Active tasks, and then select All tasks.
If you'd like to see completed tasks only, expand the filter settings and select Completed.
Let me know if you have any questions.
Golda, Jan 14, 2025