#6332: Quire Feedback
Status: To-do

On the Time Report view for projects, it would be good to be able to see the estimated time included as a column to be able to see the duration a task took as reported by users vs the time that the task was estimated to take.

As part of that, it would be good to have a further column that shows the difference between the the two (e.g. 'Actual Time Taken', or 'Difference')

Created by Thomas Brown Mar 12, 2025, Edited Mar 13, 2025

Hi,

Thank you for your feedback. In the Time Report, you can use the filter options to Group by Tasks. The difference between estimated and actual time will be displayed under Note. Feel free to give it a try!

Golda, Mar 13, 2025