Status: Open
Due: Aug 13, 2027
Assignees: Darrell Finley
If the revised accessibility regulation commences before 19 Nov, then the portal must meet WCAG 2.2 AA rather than the 2.1 AA we scoped.
Impact if it happens — remediation across roughly forty screens, plus a re-audit. Four to six weeks of unplanned work.
Response (accept, monitor) — build to 2.2 AA where it costs nothing extra now, and track the commencement date monthly rather than re-scoping on a rumour.
Trigger to watch — commencement date confirmed as earlier than 1 Nov.
Probability: Low
Type: 🔴 Risk
Impact: High
Raised On: May 7, 2027
RAID ID:
Last Reviewed: Jul 29, 2027
Type: 🔴 Risk
Impact: High
Raised On: May 7, 2027
RAID ID:
R-06
Last Reviewed: Jul 29, 2027
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026