Status: Awaiting response
Due: Jun 1, 2027
Assignees: Katherine Newman
We are assuming the client provisions a UAT environment matching production by 1 Jun 2027.
Why it matters — every date after UAT is calculated from this one. If the environment is late, the whole tail of the plan moves.
How we will validate it — written confirmation from the client's IT lead, with a named engineer and a date, not a verbal "should be fine".
If it turns out false — raise as a schedule risk immediately, and price a hosted UAT environment as the fallback.
Type: 🟡 Assumption
Impact: High
Raised On: Mar 19, 2027
RAID ID:
Depends On:
Last Reviewed: May 20, 2027
Impact: High
Raised On: Mar 19, 2027
RAID ID:
A-02
Depends On:
Client IT team
Last Reviewed: May 20, 2027
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026