Status: Escalated
Due: Apr 16, 2027
Assignees: Pak Youngjae
What happened — the shared staging environment has been unavailable since 6 Apr after a failed infrastructure upgrade. Six working days lost.
Impact — QA cannot regression-test, so sprint 8 will close with an untested increment. The debt compounds every day this runs.
Next step — infrastructure to either roll back the upgrade or stand up a temporary environment. Decision needed by 16 Apr, not "soon".
Escalated to the infrastructure lead on day four. Escalate to the steering committee if unresolved by 16 Apr.
Type: 🟠 Issue
Impact: High
Raised On: Apr 6, 2027
RAID ID:
Depends On:
Last Reviewed: Apr 15, 2027
Impact: High
Raised On: Apr 6, 2027
RAID ID:
I-01
Depends On:
Platform infrastructure team
Last Reviewed: Apr 15, 2027
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026