#21: RAID Log / 🟠 Issues — what has already gone wrong
Status: Escalated
Due: Apr 23, 2027
Tag: Budget Vendor
Assignees: Felipe

What happened — the vendor contract was agreed on 2 Apr but no budget code was opened, so the PO cannot be raised.

Impact — the vendor will not release production credentials without a PO, which blocks D-01, which blocks the whole authentication workstream.

Next step — finance to open the budget code against the portal capital line. This is an administrative unblock, not a decision, so it should take days rather than weeks.

Escalated because it has been sitting for three weeks on nobody's list.

Type: 🟠 Issue
Impact: High
Raised On: Apr 2, 2027
RAID ID:

I-05


Depends On:

Finance — budget office


Last Reviewed: Apr 15, 2027
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026