#6: RAID Log / 🔴 Risks — what could go wrong
Status: Escalated
Due: Sep 24, 2027
Tag: Schedule Technical
Assignees: Elian Glace

If the payment gateway migration is not live by 5 Nov 2027, then the switch-over falls inside the year-end change freeze and the portal launches on the legacy gateway.

Impact if it happens — launch slips to Q1 2028 and we carry the old gateway's per-transaction fee for another quarter.

Response (mitigate) — pull the migration forward into sprint 14 and run the swap behind a feature flag so it can be reversed without a release.

Trigger to watch — sandbox certification not passed by 15 Aug. If that date goes red, this risk becomes an issue.

Probability: High
Impact: Critical
Raised On: Mar 12, 2027
RAID ID:

R-01


Last Reviewed: Sep 9, 2027
Type: 🔴 Risk
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026