#17: Risk Register / Budget & Cost Risks
Status: Analyzing
Due: Sep 5, 2027
Tag: Contingency Reserved
Assignees: Katherine Newman

Risk statement. Three of the last five sprints absorbed work that was not in the approved scope baseline. At the current rate the 12% contingency reserve will be fully consumed by early October, leaving nothing for genuine unknowns.

Trigger / early warning. More than two unbudgeted requests accepted in a single sprint, or contingency drawdown passing 60%.

Consequence if realised. No financial buffer for the remaining 40% of the project. Any genuine surprise becomes an immediate escalation.

Current response. Mitigate. Formal change-control gate; anything over 3 days of effort needs written sponsor approval.

Risk ID:

R-02


Date Identified: Jul 1, 2027
Likelihood: 4 · Likely
Impact: 3 · Moderate
Response Strategy: Mitigate
Risk Score: 12
Category: Budget & Cost
Risk Level: High (10-14)
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026