#86: Risk Register / External, Market & Compliance Risks
Status: Identified
Due: Dec 15, 2027
Assignees: Sammy Walter

Risk statement. The regional office had two short outages last year. The team is hybrid and fully equipped for remote work, so the practical disruption is limited to a partial day.

Trigger / early warning. Utility provider notice of planned works, or a second unplanned outage in a quarter.

Consequence if realised. Minor. Some lost hours, no delivery impact.

Current response. Accept. Mitigation would cost more than the risk. Documented decision, reviewed quarterly. This entry exists to show what a genuine Accept looks like on a register.

Risk ID:

R-20


Date Identified: Aug 1, 2027
Likelihood: 2 · Unlikely
Impact: 2 · Minor
Response Strategy: Accept
Risk Score: 4
Category: External & Market
Risk Level: Low (1-4)