#68: Asset Upgrade & Replacement / 4. Repair Work & Inspection / Roof Repair, Building A / Active projects
Status: In Progress
Start: Sep 14, 2026 Due: Sep 25, 2026
Assignees: Darrell Finley
Section 1 (north seam) done 9/16. Section 2 (curb flashing) done 9/18, 120 sq ft of wet insulation replaced. Section 3 (south seam) waiting on a dry day.
Created by Vicky Sep 17, 2026