#79: Asset Upgrade & Replacement / 1. Project Planning / Loading Dock Upgrade, Warehouse B (multi-department) / Active projects
Status: Completed
Due: Jun 26, 2026
Assignees: Sammy Walter

$175,000 approved by the finance director 6/26 (over the $50,000 manager threshold). Phasing agreed with Warehouse Ops: docks 1 and 2 first, then 3 and 4, so two docks stay open at all times.

Created by Vicky Sep 17, 2026