Status: Backlog
Not ready — and that is the point
This is tagged Needs Refinement on purpose, as a worked example of what an unready item looks like.
Why it fails the Definition of Ready (section 5 of How to use this Agile template):
- No acceptance criteria — "rebuild navigation" could mean a week or a quarter
- Blocked by a spec and a prototype that are both unfinished
- Almost certainly larger than 8 points, so it must be split before it can enter a sprint
- No decision yet on whether existing deep links keep working
How it should be split, once the spike reports back:
- Navigation shell and routing on iOS
- Navigation shell and routing on Android
- Deep link compatibility layer
- Migrate existing screens into the new shell
Depends on
Do not pull this into a sprint to fill space. The guide explains why that habit costs more than an under-filled sprint.
Business Value: Should have
Story Points: 13
Epic: Mobile Experience
Component: iOS, Android
Story Points: 13
Epic: Mobile Experience
Component: iOS, Android
Created by Peggy Dec 1, 2021, Edited Aug 7, 2026