In our teams, some tasks is progressing, but customer needs suspending them. And customer will check these tasks for evaluation every weeks, so I can't peekabo them. I think it will solve problems if I can let a column without relation to progress. Thanks.

Created by 余澄奕 Dec 18, 2019, Edited Jun 4, 2021

Merged #2109 to this task.

Peggy, Aug 4, 2020

This sounds similar to my request. Where as whats needed here is a column without a progress indicator, I’m looking for the ability to have multiple columns with the same % because I may manage projects with two key components having a starting phase/bucket/column what have you, of 0%. Eg: Bugs |Features | WIP | Complete

KH, Jan 8, 2020

Thanks.

余澄奕, Dec 24, 2019

Hi @erinus , that's exactly the workaround I would recommend you: create another column and named it Pending, then moved it behind the Completed column. Could you please elaborate more on "a column without relation to progress"? Also, how do Pending tasks having a percentage affect you or your customers using the list/board? Does it cause confusion or any other problem? Please let us know. Thank you very much!

Peggy, Dec 23, 2019

Merged #3446 to this task.

Peggy, Aug 4, 2020

Hi @erinus , thank you for your explanation. The percentage in Project Summary stands for the completed tasks' percentage for that project. Consider Pending tasks are unfinished tasks, so they shouldn't be counted toward the percentage. Hope this makes sense.

Peggy, Dec 24, 2019

Yes, I use "Pending" for column name and put it behind "Completed" column. So we can focus on working issues and re-check with customer for pending issues every weeks.

余澄奕, Dec 18, 2019

I'm trying to replicate this, but the app won't let me reorganize the columns... can you help me?

Fabien Savy, Mar 16, 2020

Merged #4731 to this task.

Peggy, Jul 8, 2021

Hi, @peggy .

Yes, I certainly put Pending column behind Completed column now. image.jpeg

But with percentage in Pending Column, we have a wrong project progress percentage in Project Summary. image.jpeg

It lets me re-explain to customer and product manager every week, so I hope to have a column without percentage. If you have any suggestion to solve this problem, please let me know. Thanks for your help.

余澄奕, Dec 23, 2019