Dear Sir, Madam,
While trying out your product, I was looking for a way to have multiple tasks depend on a task that would have to be completed before it is possible to finish the parent task. Is there a way to have multiple parents to a task or mark a task as a dependency for a tree to be completed?
Sincerely, Wouter
⭐️ I have merged your post with this post #277 already covering this request. Feel free to add your comments to that thread.
Peggy, Jan 22, 2021
Hi Wouter, I see. Thanks for the sample example. 😃
Crystal, Nov 21, 2016
Hi Wouter,
Not only can you have siblings and parents of a task, you can have grandparents, great grandparents and so on. 😃 Like this:
May I ask how you would like task dependency to be displayed? Would a Gantt chart view with task dependency and also reminders function be what you have in mind? An example or scenario would be hugely appreciated, thanks!
Crystal, Nov 18, 2016
It's more that multiple tasks could depend on the outcome of 1 other task, that task is required to complete the other tasks.
-- A ---- AA ---- AB -- B ---- BA ---- AB
Wooter, Nov 18, 2016