#4488: Quire Feedback
Status: Completed

Eu consigo deixar sub-tarefas como dependentes de tarefas? Onde defino as predecessoras e as sucessoras?

Ex: Tenho uma tarefa pai terminando em 30/05 e a sub-tarefa filho terminando em 29/05. O correto era só conseguir encerrar a tarefa pai com a subtarefa filho concluida, correto? Como faço isso?

Como funciona as predecessoras e as sucessoras?

Created by Jsoaresjun Apr 28, 2021

⭐️ We have merged your feedback thread with #277 to consolidate all similar feedback on one main thread.

Peggy, May 13, 2021

Hi Jsoaresjun - Thank you for your feedback. I don't speak Portuguese, so I apologize if I have mistaken anything. Please let me know if I didn't answer your question.

At the moment, in Quire, you won't be able to set dependency on tasks. However, having task dependency is in our consideration for our future enhancements. There's a thread about this topic here: #277. I will let you know if we have more update information regarding this. Thank you!

Peggy, May 13, 2021