I inadvertently dragged a Task to another Task which turned it into a Subtask, and didn't realize it until the Due Dates did not match. I transferred the Subtask to another project which turned it back into a Task, and then I transferred that Task to the project it belonged to. Is there a better way to turn a Subtask into a Task?
- I tried the drag and drop method, and it didn't seem to work. I'll experiment later. BTW, I'm on Windows 7 using Firefox.
- Thanx for the key combination. Where could I have found that myself?
Thank you
Alvin Orzechowski, Jul 17, 2021
Hi Alvin - In some grouped/sorted mode, we block users to change the task order, since it might mess up the original tree structure when not in grouped/sorted mode.
So in short, if you would like to change the order of the task when in grouped/sorted mode, you cannot do so, you would need to ungroup/unsort first.
Also, you can see the full list of keyboard shortcuts here in this guide: https://quire.io/guide/keyboard-cheatsheet/
I hope this helps.
Peggy, Jul 19, 2021
Hi Alvin - There are several ways to turn a subtask to a task:
Alt+←to un-indent the task.I hope this helps.