I would like to link specific tasks, so that task B "follows on" from task A. Then if I adjust the end date of task A, task B will automatically adjust so it's start date matches.
This makes scheduling a lot easier as a task delay will automatically update the schedule for all linked tasks that follow it.
Is this possible?
Regards, Ben
Created by Ben Jones Dec 22, 2021
Hi Ben - Thank you for your feedback. Currently, task dependency is not available. This is in our consideration for our future enhancements. If we have more updates regarding this, I will let you know! 💪