Let's say I have the following

Parent task

  • Subtask A
  • Subtask B

I would like them to still be collapsible in kanban view unless they have different statuses. so let's say that I now Subtask B in progress, but Subtask A is still unfinished

In Progress column Parent task

  • Subtask B still appearing indented and attached and collapsible

In Unfinished column Parent task

  • Subtask A

That tiny gray text is just not enough of a cue and is confusing since the Parent task also appears as its own line item.

Created by Tarun Nagpal Jan 1, 2022

Hi Tarun, I'm sorry for the late reply.

Thank you for your suggestion! Currently, we have a feature called Task Bundle where you can see the parent task and the subtasks together in the same column. You can activate the Task Bundle by clicking the Board view icon and toggling on the Task Bundle.

image.png

For more information about Task Bundle, please see this guide.

You can try this feature and see if this could work for you. Please do not hesitate to let us know if you have other suggestions. Thank you.

Golda, Jan 28, 2022

Cool thanks

Tarun Nagpal, Jan 29, 2022