#5343: Quire Feedback
Status: Completed
Tag: Resolved

We've started using Quire! It seems very easy to use and helpful, but there is one thing that has me very stumped.

I can't seem to get the "My Tasks" screen to work.

When I sort by due date, the task/subtask relationship disappears and the hierarchy becomes side-by-side (I can't distinguish between tasks and subtasks). Grouping by project is easy to see, but it is not sorted by due date.

What we want to do is to be able to "immediately find the most recent task to be done" and to be able to see the dependency between tasks and subtasks.

Created by iryo May 10, 2022, Edited May 13, 2022

❤️

iryo, May 13, 2022

@Raisag Thank you, the best solution!

iryo, May 13, 2022

Hi @iryo, When in Group or Sort mode, the hierarchy of parent tasks and subtasks will not stay intact because each task will follow according to the Group or Sort criteria. You can toggle Ctrl for Windows or Alt for Mac to activate the Advanced mode to see the parent task of each task.

Check our guide for more information about Advanced mode here.

If you have any questions, please do not hesitate to let me know 😃 . Thank you!

Golda, May 11, 2022

Hi @iryo, I'm glad to hear that! If you have any questions, feel free to reach out to us. Have a great day!

Golda, May 13, 2022