Is there a possibility that only the tasks assigned to the team member or added by him can be visible to the team member?

Created by Vivek Kakar Dec 8, 2022, Edited Dec 8, 2022

Hi Vivek, Do you mean you would like your members to only view the tasks assigned to them and cannot see other tasks in the project? If so, you can invite them as external team members.

External team members can only have access to the task assigned to them. They can also add and manage subtasks from the assigned tasks.

Check out our guide here for more details about inviting external team members.

The external team is available in the Professional and above tiers and calculated towards the total purchased organization members.