Status: Awaiting response
Due: Apr 30, 2027
Assignees: Felipe
What we need — procurement desk to approve the PO for the SSO vendor contract.
Needed by 30 Apr 2027. Every week of delay pushes D-01 by the same week, and D-01 has no slack left.
Blocked by — I-05, the missing budget code.
Fallback if it is late — none worth the name. Authentication cannot be built on a sandbox tenant. This is the dependency to chase first each week.
Type: 🔵 Dependency
Impact: High
Raised On: Apr 2, 2027
RAID ID:
Depends On:
Last Reviewed: Apr 22, 2027
Impact: High
Raised On: Apr 2, 2027
RAID ID:
D-03
Depends On:
Finance — procurement desk
Last Reviewed: Apr 22, 2027
Created by Vicky Aug 7, 2026, Edited Aug 7, 2026