#25: RAID Log / 🔵 Dependencies — what we need from someone else
Status: Open
Due: Oct 15, 2027
Tag: Client
Assignees: Katherine Newman

What we need — approved copy for the three launch emails, in the client's tone and signed off by their brand lead.

Needed by 15 Oct 2027, which allows two weeks for build and testing in the email platform before go-live.

Lead time — their approval chain is four people, so ask six weeks out rather than three.

Fallback if it is late — send a plain-text notification instead. Low impact on the launch, high impact on how the launch feels.

Type: 🔵 Dependency
Impact: Medium
Raised On: Jun 11, 2027
RAID ID:

D-04


Depends On:

Client marketing team


Last Reviewed: Oct 7, 2027