#4754: Quire Feedback
Status: Completed
Although I now understand how Quire works in this respect )ad there is clearly logic to it), I still find it tricky/confusing when I sort by date (for example) and see a parent task (with a due date) but have to go looking for subtasks that I know exist (i.e. they would normally by expanded/collapsed immediately underneath). Think the same might be true the other way around? Not sure if there's any easy way to resolve this? Thanks.
Created by Neil Hart Jul 8, 2021
Hi Neil - Please try toggling on the Advanced mode and hover over the 'Subtasks' icon. Click on the subtask to navigate to that subtask. I hope this helps.
![]()
Peggy, Jul 13, 2021
Thanks Peggy. It certain does 😍
Neil Hart, Jul 22, 2021