Work Breakdown Structure Template Permalink
Use this template to break a project down into numbered levels in Quire, from the major areas at the top to work packages small enough for one person to own and estimate. The project opens in Table view, where every work package shows its budget, effort and milestone, and a formula flags the expensive ones.
You can visit the Work Breakdown Structure project and duplicate it to your workspace, so you don’t need to build everything from scratch.
You can also explore more ready-to-use templates to speed up your workflow.
Understand a Work Breakdown Structure
A work breakdown structure (WBS) splits the whole scope of a project into levels. The top level names the major areas, the middle level names the components inside each area, and the bottom level holds the work packages that get estimated, assigned and scheduled. Each item carries a number such as 1.2.3, which tells a reader exactly where it sits in the tree.
A WBS answers “what has to be produced”, not “when”. It comes before the schedule, and the schedule is built from its bottom row.
The 100 Percent Rule
The children of any item must cover all of that item’s scope, and nothing beyond it. Finish every work package under 1.2 Plumbing and plumbing is done. If something would still be missing, a work package is missing. If finishing them would also produce something plumbing never asked for, that item belongs elsewhere.
Lay Out the Breakdown
The sample is a building fit-out in three levels, and each level maps to a different Quire structure.
| Level | Quire structure | Example |
|---|---|---|
| 1. Area | Section | 1. Internal, 2. Foundation, 3. External |
| 2. Component | Root task | 1.1 Electrical, 1.2 Plumbing, 2.1 Excavate |
| 3. Work package | Subtask | 1.1.1 Rough-in electrical, 1.2.3 Test and clean |
Three sections hold six components and twenty work packages between them, numbered 1.1.1 through 3.2.5.
Collapse the components to read the breakdown at level 2, or expand them all to check level 3.
Numbering
The WBS number is part of each task name, so the hierarchy reads the same in List, Table, Board and Timeline view, in search results, and in an export. When you restructure, renumber. The numbers are the only thing that tells a reader how the pieces relate once a task is seen outside its tree.
Estimate in Table View
Table view is only available in the Professional, Premium, Enterprise plans. More information can be found on our pricing page.
Four custom fields carry the estimates, and Table view puts them beside every work package.
| Field | Type | What it holds |
|---|---|---|
| Budget | Money | The cost estimate for one work package |
| Effort | Number (percent) | How loaded the work package is, from 0 to 100 percent |
| Milestone | Select | The gate the work package belongs to: Design, Construction, Inspection or Turnover |
| Risk | Formula | 🔴 High or 🟢 Low, calculated from Budget |
Estimate on the level 3 work packages only. Level 1 and level 2 rows are containers, so their figures come from what sits beneath them, never from a number typed on top.
Effort answers “how loaded is this”, not “how many hours”. It carries conditional colors: green up to 30 percent, amber to 50, orange to 80, and red above that, so an overloaded work package shows up before anyone reads the figure.
Note: The Milestone column is a Select field that labels which gate a work package belongs to. It is separate from Quire’s built-in milestones, which mark dates on the timeline. Use the field to group and filter the breakdown, and add real milestones if you also want the gates drawn on the schedule.
The Risk Formula
Risk is one line, and nobody types into it.
Budget >= 200 ? "High 🔴" : "Low 🟢"
A work package with a budget of 200 or more is High, everything else is Low. The formula recalculates as soon as Budget changes, so the flag cannot drift away from the estimate. In the sample, nine of the twenty work packages are flagged, led by 3.1.3 Install tile at $752.
The threshold of 200 suits the small sample figures. For a real project, edit the formula on the field and set the amount your team treats as worth a second look. Every row re-scores at once.
Totals
Switch on Sum under the Budget column by hovering over the bottom row of the table, and that row becomes the total project budget. Group the table by Milestone to see what each gate costs, since every group gets its own total. Learn more about column calculations.
Tip: Want subtotals on the level 2 rows as well? Add a Formula field with SUM(descendants.{Budget}). Each component then adds up every work package beneath it, and the figure updates whenever a leaf changes. See commonly used formulas for more.
Sequence the Work
Task dependency is only available in Professional, Premium, Enterprise plan. More information can be found at our pricing page.
The breakdown says what, and task dependencies say in what order. In the sample, 1.1.1 Rough-in electrical comes before both plumbing rough-in and fixtures, and 1.2.2 Set plumbing fixtures comes before 2.1.1 Pour concrete, which comes before 2.1.2 Cure & strip forms.
Set a predecessor from the task’s detail panel, then switch to Timeline view to check that the chain reads in the order the work actually happens.
Only the work packages under 1. Internal and 2.1 Excavate carry dates in the sample. The rest are estimated but not yet scheduled, which is how a WBS usually looks before the schedule is built from it.
Sign Off the Estimates
The Approval feature is only available in Premium and Enterprise plan. More information can be found at our pricing page.
Work packages carry approval states, so an estimate can be awaiting, approved, changes requested or rejected while the work itself is still To-do. Approval is sign-off on the estimate. Status is the progress of the work. Keeping them apart means a rejected budget never gets mistaken for unfinished work.
In the sample, 2.1.1 Pour concrete has been rejected, and 1.2.1 Rough-in plumbing has changes requested on its $350 estimate. Filter by approval state before a review to see what still needs a decision.
Pull Cross-Cuts with Sublists
The tree groups work by area. Two sublists cut across it.
| Sublist | Collects | Use it for |
|---|---|---|
| 🔴 High risk | Every work package the Risk formula flags | The list to read before a budget review |
| 🏁 Turnover gate | Everything set to the Turnover milestone | The handover checklist |
Both ship as fixed lists. To keep them up to date on their own, right-click each sublist, select Edit tasks, and set pre-set filter conditions: Risk is High 🔴 for the first, Milestone is Turnover for the second. New work packages that match are then added automatically.
Keep the Breakdown Honest
Two habits keep a WBS useful after the first week.
- Break down until a work package has one owner and one number, then stop. A fourth level is usually a schedule pretending to be a breakdown.
- Renumber when you restructure. A task called 1.2.3 that now lives under 2.1 misleads everyone who reads it.
When you adapt the template:
- Different kind of project? Rename the three sections to your own level 1 areas, such as Design, Build and Launch for a product, or the deliverables of a client engagement
- Phase-based instead of deliverable-based? Use the phases as level 1 and keep the Milestone field for the gates within each phase
- Need hours rather than load? Add a Number field for estimated hours next to Effort, and keep Effort for the at-a-glance color
Read more on our blog about what a work breakdown structure is and the ways to set one up in Quire.
Start Your Breakdown
Everything on this page can be built by hand. The template is the same thing already assembled: three sections, six components, twenty work packages, four custom fields including the Risk formula, dependencies, approvals, two sublists and the how-to document.
Duplicate the Work Breakdown Structure project into your workspace, then:
- Rename the three sections to your own level 1 areas.
- Replace the components and work packages with your own, numbering each one as you go.
- Fill in Budget and Effort on every work package.
- Set Milestone on each work package to the gate it belongs to.
- Link the order of the work with dependencies, then check the chain in Timeline view.
- Raise the Risk threshold in the formula to suit your project’s figures.
Point your team at the How to use this template document. It keeps the field definitions and the two habits inside the project, for anyone who does not read this guide.
If the project still needs a charter before it is broken down, start with the Project Charter template. To track what could go wrong on the expensive work packages, pair the breakdown with the Risk Register template.
Frequently Asked Questions
What is a work breakdown structure?
A work breakdown structure (WBS) splits a project’s whole scope into numbered levels, until each item at the bottom is small enough for one person to own and estimate. It describes what has to be produced, and the schedule is built from its bottom level.
What are the three levels of a work breakdown structure?
Level 1 is the major areas, level 2 the components inside each area, and level 3 the work packages that get estimated and assigned. In the Quire template these are sections, root tasks and subtasks, numbered 1.1.1 through 3.2.5.
What is the 100 percent rule in a WBS?
The children of any item must cover all of its scope and nothing beyond it. If finishing every work package under a component would still leave something undone, a work package is missing.
How do I create a work breakdown structure in Quire?
Use a section for each level 1 area, a root task for each level 2 component, and subtasks for the level 3 work packages, with the WBS number at the start of each name. Add custom fields for Budget and Effort and fill them in on the work packages.
How deep should a work breakdown structure go?
Stop once an item has one owner and one estimate. Three levels suit most projects, and a fourth level is usually a list of scheduled steps rather than a breakdown of scope.
How do I track WBS budget and effort in Quire?
Fill in a Money field for Budget and a percentage field for Effort on the work packages only, then turn on Sum under the Budget column in Table view for the project total. A SUM(descendants.{Budget}) formula adds subtotals to the parent rows.
How does the Risk formula in the template work?
It reads Budget and returns High 🔴 for 200 or more and Low 🟢 for anything less. It recalculates whenever Budget changes, and you can raise the threshold by editing the formula on the field.
Is there a ready-made work breakdown structure template in Quire?
Yes. Visit the Work Breakdown Structure project and duplicate it to your workspace to get the three levels, twenty sample work packages, four custom fields including the Risk formula, dependencies, approvals and two sublists.