Project Status Report Template Permalink
Use this template to write a weekly project status report in Quire: one task per report, five fixed sections as its subtasks, and a RAG color and progress figures as fields. Because every report stays in the project, Table view turns the run of reports into the project’s history.
You can visit the Project Status Report project and duplicate it to your workspace, so you don’t need to build everything from scratch.
You can also explore more ready-to-use templates to speed up your workflow.
Understand a Status Report
A status report tells the people who fund or oversee a project three things: whether it is on track, what changed since the last report, and what they need to decide. Most teams send one weekly to a sponsor, a steering committee or a client, plus one at each major milestone.
The structure stays the same every time. That is what lets a reader compare this week with last week and notice what is missing.
RAG Status
The overall status is one color, judged by the project manager.
| Color | Meaning |
|---|---|
| 🟢 On track | The date and the budget hold with no help |
| 🟡 At risk | They still hold, but the slack is gone |
| 🔴 Off track | The end date or the budget moves unless someone decides something this week |
If you cannot say which color it is, it is yellow.
Lay Out the Reports
Each report is one task, and its five subtasks are the sections. Three sections split the project by time:
- This week: the report being written, and the recurring Friday task that sends it
- Previous reports: every report already sent, one per week
- Report skeleton · duplicate me: a blank report with writing prompts in each section
The sample is a website relaunch, told through six reports: a milestone report at design sign-off, three green weeks, one yellow, one red with an escalation, and the current week back to green.
Write the Five Sections
Each section is a subtask, and its description holds the text. Keep each one under about 120 words.
| Section | What it is for |
|---|---|
| 1. Overall status | The color and two sentences. A sponsor who stops reading here should still know whether the date holds |
| 2. Progress against plan | The same three lines every week: planned, done, not done and why |
| 3. Milestones | Every milestone to launch, marked Done, On track, At risk or Missed. A missed one is never deleted |
| 4. Risks and issues | A risk might happen, an issue has. Each has an owner and a date, and is closed here when it closes |
| 5. Decisions needed | The ask, the deadline and the cost of waiting. If there is nothing to decide, write None |
The skeleton’s subtasks already hold these prompts, so whoever writes the report sees the rules while writing.
Write the Ask First
Section 5 is the only part of a report that changes what happens next. Write it before the other four, then write the rest as the evidence for it.
Every ask carries a date and a cost of waiting. The red Week 43 report asks for a contractor team on standby by Monday, and spells out that approving two days later costs the launch date. “Please advise on contractors” would not have been answered in time.
Fill In the Report Fields
Seven custom fields sit on each report task. Set them before writing the sections.
| Field | Type | What it holds |
|---|---|---|
| RAG Status | Select | 🟢 On track, 🟡 At risk or 🔴 Off track |
| Period | Text | The dates the report covers, written out, since the task’s own dates are when it was written |
| Complete (pct) | Number | How far through the plan the project is, taken from the plan, not the calendar |
| Budget Used (pct) | Number | How much of the approved budget is spent or committed |
| Spend vs Progress | Formula | Whether spending is running ahead of progress |
| Next Milestone | Date | The date of the next milestone |
| Audience | Select | Sponsor, Steering committee, Client or Team |
Spend vs Progress is a formula that compares the two percentages:
{Budget Used (pct)} > {Complete (pct)} + 10 ? "🔴 Spending ahead of progress"
: ({Budget Used (pct)} > {Complete (pct)} ? "🟡 Watch" : "🟢 Spend matches progress")
Spend more than ten points ahead of progress is red, any smaller lead is yellow, and the rest is green. It is a separate check from RAG Status. In the sample, Week 43 is red but Spend vs Progress shows only Watch: the problem that week was a vendor bug, not spending.
Move the Report Through Review
The statuses follow a report’s life.
| Status | Meaning |
|---|---|
| Draft | Being written |
| In review | Waiting for a second pair of eyes before it goes out |
| Sent | Delivered to its audience |
| Acknowledged | The audience has replied |
| Skipped | No report this period, recorded so the gap is visible instead of silent |
Each week:
- Duplicate the task under Report skeleton, move the copy to This week, and rename it to the week and the project.
- Set the fields, then write the five sections.
- Move the report to In review, then to Sent when it goes out.
- Drag it into Previous reports, and mark it Acknowledged when the sponsor replies.
The Friday: send the status report task repeats every Friday. If the full report is not ready by 3 pm, the one-line version goes out anyway: the color, one sentence, the ask. A late report reads as a hidden problem.
On the Board
The Task Bundle feature is only available in Professional, Premium, Enterprise plans. More information can be found on our pricing page.
Board view builds one column per status, so it shows which report is still in review. Turn on Task Bundle from the Board icon so each report’s five sections stay inside its card instead of spreading across the columns as cards of their own.
Each card shows the report’s fields, so the current week’s color and numbers are readable without opening the task.
Each section carries a status of its own too, which lets the reviewer sign off one section at a time. In the sample, Week 44 has three sections checked and two still in review.
Read the History in Table View
Table view is only available in the Professional, Premium, Enterprise plans. More information can be found on our pricing page.
Switch to Table view, show All tasks, and collapse the reports to their top row. Each row is now one report.
Read the RAG Status column from the bottom up and it tells the project’s story: green at design sign-off, green for two weeks, yellow when migration started late, red when a vendor bug paused it, and green again once the fix landed. Complete (pct) sits beside it, climbing from 35 to 72.
A few other ways to read it:
- Sort by Spend vs Progress to find the report, or the project, spending faster than it delivers
- Group by Audience when one project reports to several people, so the sponsor version and the team version never get mixed up
- Filter by the Decision Needed tag to list every open ask, which is the steering committee’s agenda
Two sublists collect reports across the sections. Open decisions holds every report whose section 5 is still waiting for an answer. Sponsor pack · Website relaunch holds every report sent to the sponsor, oldest to newest, for opening in Table view before a steering meeting.
Keep Reports Worth Reading
Two habits make the difference between a report that gets a decision and one that gets filed.
- Send on time, even when it is thin. A one-line report on Friday beats a complete one on Tuesday.
- Never rewrite history. Last week’s report stays as it was sent. A missed milestone stays in the table, and a skipped week is marked Skipped.
When you adapt the template:
- Several projects? Add the project name to each report and group Table view by section, or run one copy of the template per project and read them side by side in a Smart Folder
- Every two weeks? Rename the Friday task, change its repeat to every two weeks, and expect each section to run a little longer
- Sponsor wants a one-pager? Send the report’s description with the five sections pasted under it. The subtasks are for writing the report, and the reader never needs to see them
Read more on our blog about writing a project status report your stakeholders will read.
Start Your Status Report
Everything on this page can be built by hand. The template is the same thing already assembled: three sections, six sample reports, the skeleton, seven custom fields including the Spend vs Progress formula, five statuses, four tags, two sublists, the recurring Friday task and the how-to document.
Duplicate the Project Status Report project into your workspace, then:
- Delete the sample reports in This week and Previous reports.
- Rename the skeleton task to your project, and adjust the section prompts if your sponsor expects something different.
- Reassign the Friday: send the status report task to whoever writes the report.
- On Friday, duplicate the skeleton and write the first report.
Point your team at the How to use this template document. It keeps the section rules and field definitions inside the project, for anyone who does not read this guide.
To set the scope and the sponsor before the first report, start with the Project Charter template. To keep the risks in section 4 from living only in prose, pair the reports with the RAID Log template.
Frequently Asked Questions
What is a project status report?
A project status report is a short, regular update telling a sponsor or client whether the project is on track, what changed, and what they need to decide. In the Quire template each report is one task with five section subtasks.
What should a project status report include?
Five sections: overall status, progress against plan, milestones, risks and issues, and decisions needed. Record the period, percent complete, budget used and next milestone as fields beside them.
What does RAG status mean in a project report?
RAG stands for red, amber and green. Green means the date and budget hold, amber means the slack is gone, and red means something moves unless a decision is made this week.
How do I write a project status report in Quire?
Duplicate the report skeleton, set the fields, then write the five sections with the decisions section first. Move the report from In review to Sent, and to Acknowledged when the sponsor replies.
How does the Spend vs Progress formula work?
It compares Budget Used (pct) with Complete (pct). Spend more than ten points ahead is red, any smaller lead is yellow, and the rest is green.
How often should a project status report be sent?
Weekly suits most projects, plus one report at each major milestone. Send on the same day every time, and mark a missed week Skipped so the history stays complete.
How do I track status report history in Quire?
Keep every report as its own task and move it to Previous reports once sent. In Table view, the RAG Status column read from the bottom up shows the project’s story.
How do I show the five sections of a report on a board in Quire?
Turn on Task bundle from the Board icon in Board view. Each report’s sections then stay inside its card instead of appearing as separate cards.
Is there a ready-made project status report template in Quire?
Yes. Visit the Project Status Report project and duplicate it to your workspace to get six sample reports, a report skeleton, seven custom fields including the Spend vs Progress formula, and a recurring Friday task.